Project Name | District | Type of Project | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | Physical Progress % | |
From | To | |||||||
Central Province | ||||||||
Matale WS | Matale | Augmentation | 15,000 | Jan 1999 | Apr 2014 | 384.9 | 347.85 | 90 |
Kundasale Integrated WS - Stage II | Kandy | Augmentation | 130,000 | Jan 1998 | Dec 2014 | 1,400.00 | 1,276.73 | 85 |
Marassana WS | Kandy | New | 25,000 | Jan 1996 | Dec 2014 | 222 | 282.12 | 95 |
Thalawakele/ Lindula WS | Nuwara Eliya | Augmentation | 15,000 | Jan 2000 | Dec 2014 | 172 | 188.69 | 90 |
Palapathwela WS | Matale | Extension | 22,000 | Jan 2000 | Dec 2014 | 150 | 159.15 | 80 |
North Central Province | ||||||||
Hingurakkoda WS | Polonnaruwa | Augmentation | 6,000 | Jan 1996 | Dec 2015 | 130 | 124.94 | 98 |
Minneriya WS - Stage II | Polonnaruwa | Augmentation | 69,000 | Jan 2007 | Dec 2015 | 100 | 102.58 | 97 |
Medirigiriya WS - Stage I | Polonnaruwa | New | 60,000 | Jan 2007 | Dec 2015 | 638 | 574.66 | 70 |
Mahanelubewa WS | Anuradhapura | New | Dec 2010 | Dec 2014 | 129.7 | 113.74 | 97 | |
Ippalogama Housing Scheme WS | Anuradhapura | Extension | 18,000 | Jan 2007 | Dec 2014 | 798 | 598.12 | 92 |
Parasangaswewa | Anuradhapura | New | 1,000 | Jan 2013 | Dec 2013 | 31.6 | - | |
Deyata Kirula | Jan 2011 | Dec 2012 | 830 | 528.67 | 85 | |||
Eastern Province | ||||||||
Kantale WS | Trincomalee | Augmentation | 25,000 | Jan 1999 | Dec 2012 | 274.8 | 216.37 | 69 |
Tampalakamam WS | Trincomalee | Augmentation | 30,000 | Jan 1999 | Dec 2011 | 95.2 | 85 | 100 |
Transmission Main from Kantale to Tampalakamam | Trincomalee | Jan 2012 | Jan 2014 | 1,397.80 | 450 | 80 | ||
Wadinagala/ Wan - Ela WS | Jan 2012 | Dec 2015 | 808.5 | 19.04 | 10 | |||
Serunuwara WS | Trincomalee | Augmentation | 9,500 | Jan 2001 | Dec 2013 | 110.1 | 106.28 | 48 |
Dehiattakandiya WS - Stage I & II | Ampara | Augmentation | 16,000 | Jan 2007 | Dec 2012 | 300 | 250.74 | 99 |
Deyata Kirula 2013 | Ampara, Trincomalee | Jan 2012 | Dec 2013 | 1,875.00 | 26.89 | |||
Northern Province | ||||||||
Wastewater Treatment Plant for Kilinochchi Hospital | Jan 2012 | Dec 2012 | 36 | 6.95 | ||||
Mahawa/ Wariyapola/ Nikaweratiya WS | Jan 2012 | Dec 2014 | 505 | 40.7 | 90 | |||
North Western Province | ||||||||
Ibbagamuwa WS | 2012 | Dec 2014 | 239 | 62.02 | 4 | |||
Divulagane WS | Kurunegala | New | 1,950 | Jan 2013 | Oct 2015 | 46.7 | - | |
Dambadeniya | Jan 2012 | Dec 2016 | 796 | 3.26 | 2 | |||
Mahawa/ Wariyapola/ Nikaweratiya WS | Kurunegala | Augmentation | 45,000 | Jan 2000 | Dec 2014 | 996.7 | 856.31 | 89 |
Sabaragamuwa Province | ||||||||
Embilipitiya WS | Ratnapura | Augmentation | 84,000 | Sep 2003 | Dec 2013 | 363 | 387.88 | 94 |
Pelmadulla WS | Ratnapura | Augmentation | 14,500 | Jan 2000 | Dec 2015 | 384.2 | 355.47 | 96 |
Nivithigala WS | Ratnapura | Augmentation | 14,500 | Jan 1999 | Dec 2013 | 99.1 | 70.01 | 58 |
Udawalawa WS Stage I & II | Ratnapura | Augmentation | 9,400 | Jan 1999 | Dec 2014 | 973.6 | 654.59 | 90 |
Yatiyantota WS | Kegalle | Augmentation | 9,400 | Sep 2003 | Dec 2012 | 165.8 | 176.6 | 85 |
Godakawela WS | Ratnapura | Augmentation | 22,500 | Jan 1999 | Dec 2011 | 288.8 | 211.63 | 98 |
Pattampitiya WS | Kegalle | Extension | 7,300 | Jan 2001 | Dec 2011 | 145.2 | 143.61 | 100 |
Galigamuwa WS | Kegalle | New | 30,800 | Jan 2011 | Dec 2014 | 841 | 219.11 | 36 |
Madola WS | Kegalle | New | 4,500 | Jan 2013 | Dec 2013 | 132 | - | |
Kiriella WS | Ratnapura | 7,300 | Jan 2011 | Dec 2014 | 205 | 21.92 | 97 | |
Southern Province | ||||||||
Akuressa WS | Matara | New | 15,000 | Jan 1999 | Dec 2011 | 338.6 | 272.66 | 100 |
Thihagoda WS | Matara | New | 7,500 | Jan 2001 | Dec 2011 | 162.1 | 172.46 | 100 |
Baddegama WS | Galle | New | 33,830 | Jul 2013 | Aug 2015 | 441 | ||
Gonapinuwala WS | Galle | New | 20,825 | Jul 2013 | Aug 2015 | 350 | ||
Dikkumbura WS | Galle | New | 17,130 | Jul 2013 | Aug 2015 | 275 | ||
Bentota WS | Galle | New | 18,850 | Jul 2013 | Aug 2015 | 700 | ||
Udugama WS | Galle | New | 6,000 | Apr 2001 | Dec 2011 | 145.5 | 139.51 | 100 |
Pitabeddara WS | Matara | New | 6,000 | Jan 2001 | Dec 2011 | 130.3 | 102.5 | 98 |
Bonavista Kanda Area WS | Matara | 600 | Jan 2010 | Dec 2012 | 57 | 44.03 | 99 | |
Hakmana WS | Matara | 10,000 | Jan 2008 | Dec 2013 | 383.4 | 123.76 | 60 | |
Uva Province | ||||||||
Ohiya Transmission | Badulla | New | 10,000 | Feb 1999 | Dec 2013 | 264.7 | 206.23 | 96 |
Monaragala WS - Stage II | Monaragala | New | 10,000 | Jun 1999 | Dec 2013 | 154.8 | 142.17 | 98 |
Badalkumbura WS | Monaragala | New | 22,000 | Oct 1999 | Dec 2013 | 124.4 | 97.18 | 86 |
Buttala WS | Monaragala | 2,600 | Jan 2010 | Dec 2012 | 295 | 287.44 | 100 | |
Ambagasduwa WS | Badulla | New | 6,000 | Jun 1999 | Dec 2013 | 382 | 137.22 | 72 |
Wellawaya WS | Monaragala | Augmentation | 6,000 | Jan 2007 | Dec 2014 | 250 | 96.81 | 65 |
Western Province | ||||||||
Rehabilitation of Western Central WS | Colombo | Rehabilitation | 162,500 | 2009 | Dec 2012 | 1,300.00 | 1,317.51 | 97 |
Kirindiwela WS | Gampaha | New | 8,000 | May 1998 | Dec 2013 | 198 | 172.63 | 90 |
Nittambuwa/ Veyangoda WS | Gampaha | Augmentation | 15,000 | Oct 1999 | Dec 2013 | 210.7 | 201.96 | 96 |
Kalutara Integrated WS - Stage II | Kalutara | Augmentation | 210,000 | Jan 2008 | Dec 2014 | 1,366.20 | 789.16 | 58 |
Jalthara - Ranala WS | Colombo | 17,920 | Jan 2010 | Dec 2013 | 217.2 | 86.15 | 27 | |
Katunayake WS - Stage WS 1 & II | Gampaha | Augmentation | 29,000 | Jan 2005 | Dec 2014 | 470 | 265.03 | 62 |
Kolonnawa Sewerage | Colombo | New | 20,000 | 1,296.00 | - | |||
Inter Provincial Projects/ Programmes | ||||||||
Small Schemes & Disaster Management Programme and Urgent Improvements (TCE Less than Rs.10 M ) a. Madola b. PahalaKaduganna c. Eheliyagoda d. Extension to Batuwatta & Kopparamessa e. Menikdola f. Kabagamuwa g. Makurakanda h. Ellawala |
10,000 | Jan 2010 | Dec 2012 | 92.5 | 88.9 | |||
Investigations, Surveys & Feasibility Studies for new project proposals | 100 | 12.55 | ||||||
Utility shiffting / replacement owing to accelerated Pradeshiya Sabha Road Development Programmmes | 300 | 25.05 |
* Abbreviations | ||
WS | : | Water Supply |
Emerging small townships Water Supply Projects Click here.....
Name | |
ADB V(a) | Click here..... |
(b) | Click here.... |
(c) | Click here..... |
Ampara JICA | Click here..... |
Ampara Phase III | Click here..... |
Anuradhapura | Click here..... |
Badulla | Click here..... |
CWSSP | Click here..... |
Dambulla | Click here..... |
GColombo | Click here..... |
Jaffna | Click here..... |
Kalatuwawa | Click here |
Kalu Ganga | Click here..... |
Kilinochchi | Click here..... |
Kolonna | Click here..... |
Mahiyangana | Click here..... |
Monaragala | Click here..... |
Project Name (Donor) | District | Type of Project | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | Physical Progress % | |
From | To | |||||||
Central Province | ||||||||
Water Sector Development Project 1 Sub Project 4 Greater Kandy WS Phase I Stage II (JICA) | Kandy | Augmentation | 616,000 | Oct 2007 | Jul 2012 | 4,164.00 | 4,681.63 | 94 |
Greater Dambulla WS - Stage 1 (INDIA) | Nuwara Eliya | Augmentation | 2012 | Jul 2014 | 9,593.00 | 5,808.50 | 23 | |
Eastern Province | ||||||||
Eastern Coastal Towns of Ampara District (ECTAD) WS Phase II (Australia) | Ampara | New | 161,400 | Oct 2002 | Dec 2010 | 11,078.20 | 10,712.13 | 100 |
Eastern Province Water Supply Development Project (JICA) | Ampara | New | 2010 | 2015 | 6,526.00 | 1,407.16 | 70 | |
Integrated Water Supply Scheme for the Unserved Area of Ampara District Phase III (Australia) | Ampara | New | 80,000 | 2007 | 2015 | 18,012.00 | 9,904.30 | 36 |
Northern Province | ||||||||
Jaffna Killinochchi Water Supply & Sanitation (ADB VI) | Jaffna | Augmentation | 15,000 | 2011 | 2016 | 18,328.20 | 194.56 | 15 |
Killinochchi Rehabilitation Water Supply Project (JICA) | 15,000 | 2013 | 2015 | 1,900.00 | - | |||
Immediate Arragements to provide Water Supply to Kilinochchi (New 2 KR) (JICA ) | 2013 | 2015 | 260 | 150 | 65 | |||
North Central Province | ||||||||
Thambuttegama WS (China) | Kurunegala | New | 2014 | 2017 | 1,805.00 | - | ||
Anuradhapura North Intergrated Water Supply (JICA) | 2013 | 2015 | 9,736.00 | - | ||||
Southern Province | ||||||||
Ruhunupura WS Development (Korea) | Jan 2011 | Mar 2013 | 13,131.30 | 5,378.20 | 46 | |||
Kirama, Katuwana, Middeniya & Angunakolapelessa Integrated WS (China) | Galle | Augmentation | 160,000 | Jan 2012 | Jan 2013 | 2,662.00 | - | |
Rehabilitation & Augmentation of Kirindioya Water Supply (Austria) | Hambantota | Augmentation | 30,000 | Feb 2007 | Dec 2009 | 2,104.83 | 1,914.25 | 100 |
Uva Province | ||||||||
Badulla - Haliela and Ella Integated WS (US Exim Bank) | 2013 | 2015 | 10,396.50 | 5.1 | ||||
Mahiyangana Water Supply (Austria) | 2013 | 2016 | 1,785.00 | - | ||||
Western Province | ||||||||
Water Sector Development Project I Towns North of Colombo WS -stage II (JICA) |
Colombo | Extension | 200,000 | 2007 | 2014 | 6,490.00 | 5,750.36 | 97 |
Kelani Right Bank WTP (DANIDA) | Colombo | New | 1,500,000 | Oct 2008 | Dec 2013 | 12,000.00 | 9,477.31 | 98 |
Rehabilitation & Augmentation of Labugama - Kalatuwawa WTP (Hangary) | Colombo | Rehabilitation | 375,000 | 2013 | 2016 | 8,100.00 | 1.29 | - |
Augmentation of Negombo WS (DUTCH) | Gampaha | Augmentation | 137,500 | 2008 | 2013 | 7,302.00 | 6,703.69 | 98 |
Water Sector Development Project I Greater Colombo Water Rehabilitation (JICA) |
Colombo | Rehabilitation | 100,000 | 2007 | 2015 | 4,785.00 | 3,476.78 | 74 |
Water Sector Development Project II (JICA) Kaluganga Water Supply Project Phase I -Stage II & Non Revenue Water Reduction in Colombo City (NRW Master Plan) |
Jul 2008 | Dec 2015 | 10,846.00 | 4,650.60 | 66 | |||
Consultancy Services for Non Revenue Water (NRW) Engineering Study, Master Plan Update and Institutional Development | Oct 2011 | Jun 2013 | 412.1 | - | ||||
Energy Conservation Project at Ambatale WTP (GERMAN) | 2012 | 2014 | 6,220.00 | - | ||||
Capacity Development Project for NRW reduction in Colombo City (JICA) | 2010 | 2011 | 201 | 30.6 | 100 | |||
Colombo Water Supply Service Improvement Project (ADB) | 2012 | 2018 | 28,800.00 | 8.12 | ||||
Katana WS (China) | 2014 | 2015 | 1,641.00 | - | ||||
Water Treatment Facilities Moratuwa / Panadura, Ambatale and in Negombo (Spanish) [formerly Galagoda WSS] | Colombo, Gampaha | New | 10,000 | Oct 2007 | Dec 2009 | 2,690.00 | 2,672.34 | 100 |
Sabaragamuwa Province | ||||||||
Greater Ratnapura Water Supply Project (Spain) | Jan 2012 | Dec 2016 | 9,928.00 | - | ||||
Kolonna/ Balangoda Water Supply Project (Belgium) | 2011 | 2015 | 4,658.00 | 1,244.50 | 5 | |||
North Western Province | ||||||||
Greater Kurunegala (China) | Jan 2013 | Dec 2015 | 11,943.00 | - | ||||
Wandura Pinu Ella WS (China) | Jan 2012 | 9,756.00 | - | |||||
Inter Provincial Projects/ Programmes | ||||||||
Secondary Towns Rural Community Based WS & Sanitation (ADB 4th project) | Polonnaruwa, Anuradhapura, Trincomalee, Hambantota, Batticaloa | New | 968,000 (Water) & 171,500 (Sanitation) | Jan 2004 | 2013 | 29,680.00 | 25,692.94 | 95 |
Dry zone urban Water & Sanitation Project(ADB V) | 86,000 | Jun 2009 | Jun 2014 | 13,029.60 | 1,494.19 | 31 | ||
Hambantota/ Ambalantota/ Weligama/ Kataragama Implementation Project & Badulla, Bandarawela Integrated Feasibility Studies (UNIHA) | Hambantota, Matara | Augmentation | 150000 & SLI 200,000 | Nov 2004 | Dec 2013 | 2,126.00 | 1,767.88 | 98 |
* Abbreviations | ||
ADB | : | Asian Development Bank |
DANIDA | : | DANish International Development Agency |
JICA | : | Japan International Cooperation Agency |
KfW | : | Credit for Reconstruction |
SLI | : | Service Level Improvements |
UNICEF | : | United Nations International Children's Fund |
WS | : | Water Supply |
Project Name | District | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | |
From | To | |||||
Water Sanitation & Hygine Programme (WASH program) | Mulaitivu, Ampara, Hambantota, Kalutara, Tangalle & Thirukkovil | 2011 | 2013 | 240 | 141.57 | |
Tsunami Affected Areas Rebuilding Fund Project - Component D (ADB) | Trincomalee, Batticaloa & Hambantota | 14253 families | 2,005 | 2011 | 1,230.00 | 919.78 |
Assistance for Emergency Measures and Ambalangoda WSS (KfW) | Galle | 2,007 | 2011 | 4,201.70 | 4,898.52 | |
Trincomalee Integrated Infrastructure Project (French Development /Agency - AFD-Component 2) | Trincomalee | 2006 | 2013 | 2,819.30 | 1,983.18 | |
IFRC Funded Tsunami Transmission System Improvement (IFRC) | Jaffna, Ampara, Hambantota, Matara & Galle | 2005 | 2011 | 3,785.00 | 2,422.16 | |
Greater Trincomalee Integrated Water Supply (RPE France) | Trincomalee | 2,006 | 2013 | 2,881.00 | 2,011.17 |
* Abbreviations | ||
ADB | : | Asian Development Bank |
IFRC | : | International Federation of Red Cross |
KfW | : | Reconstruction Credit Institute |
UNICEF | : | United Nations International Children's Fund |
USAID | : | United States Agency for International Development |
Project Name | District | Type of Project | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | Physical Progress % | |
From | To | |||||||
Central Province | ||||||||
Water Sector Development Project 1 Sub Project 1 Sewage disposal system for Kandy Municipal area (JICA) |
Kandy | New | 49,700 | Oct 2007 | Dec 2017 | 22,585.00 | 797.99 | 3 |
Southern Province | ||||||||
Galle Sewerage (China) | Galle | 2010 | 2014 | 3,200.00 | - | |||
Kataragama Sacred City Waste Water Disposal | Monaragala | Augmentation | 15,000 | 615.0 | ||||
Western Province | ||||||||
Rehabilitation & Upgrading of Southern Catchments of GC Sewerage (Austrian) | Colombo | Rehabilitation | 300,000 | 2007 | 2010 | 2,222.00 | 1,881.87 | 100 |
Waste Water Disposal System for Ratmalana/ Moratuwa & Ja-Ela/ Ekala Areas (SIDA) | Colombo | New | 94,500 | 2008 | 2013 | 16,155.00 | 12,695.26 | 85 |
Greater Colombo Waste Water Managemet (ADB) | Colombo | Rehabilitation | 500,000 | 2010 | 2014 | 1,012.00 | 36.98 | 2 |
GPOBA funded project for increasing Household Access to Sewerage Services (World Bank) | 2012 | 2014 | 1,095.00 | 3.06 | ||||
Maharagama Boralesgamuwa (China) | 2013 | 2015 | 2,200.00 | - | ||||
Hospital Sewerage System Improvement (China) | 2012 | 2,100.00 | - | |||||
North Western Province | ||||||||
Greater Kurunegala Water Supply & Sanitation | Kurunegala | Augmentation/ New | 64,000 | 8,283.0 |
* Abbreviations | ||
ADB | : | Asian Development Bank |
DANIDA | : | DANish International Development Agency |
JICA | : | Japan International Cooperation Agency |
SIDA | : | Swedish International Development Cooperation Agency |
WS | : | Water Supply |
Global partnership on Output Based - Aid project is implementing under the funds from World Bank, GOSL, NWSDB. Main objectives of the project are to increase house hold Access to domestic sanitation in Greater Colombo for low income households.
It is targeted to give 8800 hoseholds sanitation facilityes and it will be benefited for 44000 people in Dehiwala/Mt. Lavinia, Kolonnawa, Moratuwa and Jaela/Ekala area.
Details of GPOBA Project and SPEARs | |
Spear Badovita | Download |
Spear DC | Download |
Spear Diyawarapura | Download |
Spear Lunawa | Download |
Spear On-Site | Download |
Spear SCE Stage | Download |
Spear Tsunami | Download |
Resettlement Plan Click here.....
Environmental Impact Assessment Report click here.......
THE GOVERNMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA
MINISTRY OF CITY PLANNING AND WATER SUPPLY
NATIONAL WATER SUPPLY AND DRAINAGE BOARD
Date : 08/02/2017
Loan No. & Title : ADB Loan No. 3030-SRI;
AFD Loan No.:- CLK 1008 – 01P AFD Credit Facilities
Greater Colombo Water and Wastewater Management Improvement Investment Programme - Project 2;
AFD Contractual Co Financing - Ambathale Water Supply System Improvement & Energy Saving Project
Contract No. : GCWWMIIP/AFD/EQUIP/OPER/ICB/06
Title :Bidding Document for Machinery and Equipment for Operation and Maintenance Activities of Western Production Section
Deadline for Submission of Bids: 29/03/2017, 10:00 hours (Local time)
Please refer the attached IFB for more details.Click here.....