Objective
Management of value chain effectively and efficiently for timely delivery of services to the internal and external stakeholders.
Key Functions
- Drafting Subsidiary Loan Agreements with External Resource Department.
- Coordination with National Planning Department for Project formulation.
- Coordination with the Ministry for Project Development and Formulation.
- Business Plan Development and follow-up of Business Strategies.
- Donor Coordination, Facilitation and providing secretariat assistance to ERD.
- Coordination with Conventional Donors (ADB/ AFD etc.)
- Investment portfolio management
- Sector policy formulation and Development of Guidelines.
- Development of Public Private Partnership Models (PPP/ BOT)
- Coordination with Attorney General's Department with regard to Contract Document finalization.
- Maintaining and updating Database of priority water supply projects.
- Coordination of EOI processing.
Downloads
No |
Project |
Total Estimated Cost(Rs. Min) |
Funding Source |
Population Served at Reaching the Design Horizon |
|
JICA / Korean Projects |
1 |
Deduruoya |
8,430 |
Korea EDCF |
90,729 |
2 |
Ruwanwella |
2,980 |
Korea EDCF |
39,960 |
3 |
Kaluganga Phase II |
38,915 |
JICA |
1,392.000 |
|
Foreign Funded CKD Area Water Supply Projects |
4 |
Anuradhapura North Phase II |
7,458 |
JICA |
115,600 |
5 |
Polonnaruwa East |
57,000 |
China |
345,471 |
6 |
Greater Anuradhapura North & Trincomalee |
53,113 |
Australia |
171,525 |
7 |
Anuradhapura South |
18,600 |
China |
280,956 |
8 |
Thambuttegama |
17,492 |
China |
91,810 |
9 |
Eppawala, Rajanganaya, Nochchiyagama, Giribawa Integrated WSP |
52.046 |
Israel |
267,327 |
|
Foreign Funded Water Supply Project Other than CKD |
10 |
Greater Matale |
24,631 |
France |
400,000 |
11 |
Aluthgama, Mathugama, Agalawaththa (Kalutara Phase III) |
28,174 |
India |
450,000 |
12 |
Polgahawela, Pothuhera & Alawwa Int |
15,684 |
India |
180,000 |
13 |
Kelani Right Bank - II |
26,556 |
France |
1,744,000 (Service improvement) |
14 |
Gampaha, Attangalla, Minuwangoda Integrated WSP |
33,330 |
China |
519,580 |
15 |
Kandy North |
40,360 |
China |
450,000 |
16 |
Kundasale Haragama |
29,753 |
India |
300,000 |
17 |
Anamaduwa |
6,722 |
Spain |
81,741 |
18 |
Katana |
9,346 |
China |
93,105 |
19 |
Hemmathagama |
16,448 |
Netherlands |
169,200 |
20 |
Dankotuwa |
15,500 |
Belgium |
314,000 |
21 |
Ambathale, Orugodawaththa Pipe Shifting |
8,578 |
Austria |
(Service Improvement) |
22 |
Makandura, Pannala, Kuliyapitiya |
8,100 |
India |
112.000 |
|
Local Bank Funded Project |
23 |
Matara Stage IV |
12,886 |
NDB |
160,800 |
24 |
Pitigala, Dikkumbura, Uragasmanhandiya (Galle Cluster Project) |
1,755 |
BOC PB |
115,038 |
25 |
Attampitiya |
2,244 |
People's Bank |
15,700 |
|
Total |
588,082 |
|
7,900.542 |
|
Total Excluding Service Improvement Projects and Kaluganga Phase II |
|
|
4,764,542 |

No |
Project |
Population to be Served |
TEC(LKR million) |
FF Projects |
1 |
Valachchanei WSP |
120,000 |
16,000.00 |
2 |
Hatharaliyadda Water Supply Scheme |
27,042 |
1,702.00 |
3 |
Mirigama, Kandalama, Kaleliya & Gangegoda Group of Town WSS. |
52,000 |
1,530.00 |
4 |
Kirama, Katuwana WSP |
36,495 |
1,782.00 |
5 |
Construction of Kelani Ganga Vee Oya Upstream Reservoir |
- |
10,300.00 |
6 |
Construction of(Dam) Yatimahana Reservoir in Maha Oya. |
- |
8,325.00 |
7 |
Imaduwa WSP |
22,000 |
1,130.00 |
8 |
Kalpitiya WSP |
72,000 |
12,810.00 |
9 |
Delthota WSP |
30,272 |
4,731.00 |
10 |
Pothuvil, Siyambalanduwa WSP (from Heda oya reservoir) |
|
20,000.00 |
11 |
*Divulapitiya WSP |
88,229 |
5,000.00 |
12 |
Enhancement of Greater Colombo Treated Water Storage. |
|
2,192.00 |
13 |
Partial Treatment |
49,100 |
16,085.00 |
14 |
Katupotha, Bamunakotuwa, Panduwasnuwara WSP. |
179,745 |
22,031.00 |
15 |
Puttalam(South) WSP |
190,500 |
14,240.00 |
16 |
Mannar WSP |
160,491 |
18,553.00 |
17 |
Vavuniya WSP |
290,922 |
12,576.42 |
18 |
Kallaru Rural Water Supply Scheme |
1,200 |
57.00 |
19 |
Muruthawela WSP |
27,600 |
- |
20 |
Gawarammana, Bogahakumbura Integrated WSS |
62,162 |
4,110.00 |
21 |
Badalkumbura Alupotha Integrated WSS |
60,250 |
2,906.00 |
22 |
Kiriibbanwewa WSS |
12,627 |
2,708.00 |
|
Sub Total |
1,482,635.00 |
178,768.42 |
CKD Projects |
1 |
Ulhitiya WSP |
|
1,422.00 |
2 |
Thaldena WSP |
19,406 |
2,402.00 |
|
Sub Total |
19,406.00 |
3,824.00 |
LBF Projects |
Distribution Laying of Ongoing Foreign funded Projects |
1 |
Ratnapura Distribution |
116,600 |
3,000.00 |
2 |
Kolonna Balangoda Distribution |
40,000 |
6,000.00 |
Mahiyanganaya Extension to Ridimaliyadda |
28,500 |
Badulla Haliela Extention WSP |
40,000 |
Monaragala Distribution |
30,000 |
3 |
Dambulla Distribution |
83,280 |
900.00 |
|
Sub Total |
|
9,900.00 |
Other Local Bank Funded Projects |
4 |
Galgamuwa integrated WSS |
20,000 |
6,000.00 |
5 |
Ampara Extension II |
54,000 |
5,000.00 |
6 |
Kotmale Riverside WSP |
2,000 |
1,969.00 |
7 |
Hasalaka WSP |
49,370 |
850.00 |
8 |
Giridara WSP |
25,575 |
875.00 |
9 |
Kondadeniya WSS |
17,666 |
1,662.00 |
10 |
Greater Galle St.III |
330,000 |
7,975.00 |
11 |
Nanuoya WSP |
18,000 |
959.00 |
12 |
Deniyaya WSP |
16,878 |
625.00 |
13 |
Padalangala WSP |
1,000 |
16,500 |
14 |
Morawaka, Barawakumbura Rotte WSPs |
39,512 |
1,758.00 |
15 |
Urubokka WSP |
10,163 |
680.00 |
|
Sub Total of Other LBF Projects |
|
44,853.00 |
|
Sub Total of LBF Projects |
922,544.00 |
54,753.00 |
PPP Projects |
1 |
Weliwita WSP |
- |
48,221.00 |
|
Sub Total |
- |
48,221.00 |
JICA, ADB Projects |
1 |
Bandarawela, Haputale, Diyathalawa Int. WSP (ADB) |
141,000 |
16,230.00 |
2
|
Weliwita Distribution (ADB) |
- |
10,987.00 |
3 |
Ruhunupura St. II(ADB) |
114,054 |
7,840.55 |
4 |
Eheliyagoda(ADB) |
121,526 |
4,474.54 |
5 |
Kalpitiya WSP (ADB) |
6,749 |
376.00 |
6 |
Construction of Salinity Barrier Across Kaluganga (JICA). |
|
5,000.00 |
|
Sub Total |
383,329.00 |
44,908.09 |
|
Grand Total |
2,807,914.00 |
330,474.51
|