Project Name | District | Type of Project | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | Physical Progress % | |
From | To | |||||||
Central Province | ||||||||
Water Sector Development Project 1 Sub Project 1 Sewage disposal system for Kandy Municipal area (JICA) |
Kandy | New | 49,700 | Oct 2007 | Dec 2017 | 22,585.00 | 797.99 | 3 |
Southern Province | ||||||||
Galle Sewerage (China) | Galle | 2010 | 2014 | 3,200.00 | – | |||
Kataragama Sacred City Waste Water Disposal | Monaragala | Augmentation | 15,000 | 615.0 | ||||
Western Province | ||||||||
Rehabilitation & Upgrading of Southern Catchments of GC Sewerage (Austrian) | Colombo | Rehabilitation | 300,000 | 2007 | 2010 | 2,222.00 | 1,881.87 | 100 |
Waste Water Disposal System for Ratmalana/ Moratuwa & Ja-Ela/ Ekala Areas (SIDA) | Colombo | New | 94,500 | 2008 | 2013 | 16,155.00 | 12,695.26 | 85 |
Greater Colombo Waste Water Managemet (ADB) | Colombo | Rehabilitation | 500,000 | 2010 | 2014 | 1,012.00 | 36.98 | 2 |
GPOBA funded project for increasing Household Access to Sewerage Services (World Bank) | 2012 | 2014 | 1,095.00 | 3.06 | ||||
Maharagama Boralesgamuwa (China) | 2013 | 2015 | 2,200.00 | – | ||||
Hospital Sewerage System Improvement (China) | 2012 | 2,100.00 | – | |||||
North Western Province | ||||||||
Greater Kurunegala Water Supply & Sanitation | Kurunegala | Augmentation/ New | 64,000 | 8,283.0 |